Having designed, drawn and printed most of the Southwold Railway goods stock (eg see How I designed and constructed Southwold long wheelbase van, short wheelbase van, two plank open, and four plank open wagons), it was inevitable that I would attempt to design, draw, print and assemble at least one of the Southwold Cleminson six wheeled coaches.
Background information
The Southwold was one of the few narrow gauge railways in the UK (apart from the NWNG Railway and the Manx Northern) to use six wheeled coaches using the Cleminson system.
6-wheeled coaches at Southwold Source: https://lightmoor.co.uk/BDLbooksample_pics/L8429_samp2.jpg |
The design, whilst ingenious, never really caught-on. Long term analysis showed that wear on track and wheel flanges was quite excessive and so four wheeled bogies became the norm - though in the UK some standard gauge six wheeled wagons (eg milk tankers) and vans (eg parcels vans) persisted well into the 1970s and 1980s.
Six-wheeled milk tanker wagon Source: https://didcotrailwaycentre.org.uk/shopimages/articles/extra/4409_01.jpg |
The principle of the design is quite simple. The axles on the end of the wagon or coach swivel around a central pivot - while the central axle slides from side to side. The trucks on which the axles are mounted are connected to each other with a simple linkage.
As the wagon or coach rounds a curve, the centre truck slides sideways and the linkages force the outer trucks to pivot.
In reality, the centre truck does not normally slide outside the sides of the wagon or coach frame - the above diagram is to emphasise the effect. However, as we shall see below, this projection of the centre truck beyond the side frames did need to be incorporated into my design.
Developing a working chassis
Creating a working chassis was achieved very much by trial and improvement. My aim was to try and replicate the original Cleminson mechanism as faithfully as possible. However, the original design must have been developed to cope with broader radius curves and far less undulating track than that which is found on the Peckforton Light Railway.
Sharp curves
To deal with my tight radius curves, I needed to allow the centre truck to swing out far more than the design of the prototype would have accommodated, as indicated above.
I experimented with various designs of centre truck but eventually I had to compromise between prototypical appearance and performance. The centre truck is wider than the the coach body and so projects slightly beyond it when travelling along straight track.
This is to allow the truck to slide further than it would on the real thing when taking the tighter curves on my railway.
Undulations
Once I had cracked the design of the centre truck to tackle tight curves, I quickly realised that I also needed to compensate for the ups and downs of my trackwork. Because the wheelbase of the coach from one end truck to the other is quite large (364mm), there can sometimes be quite a large variation in the level of the track beneath the centre truck between them.
For example, when a coach is breasting the summit of a slope or travelling over a hump, the centre truck can act like the pivot of a see-saw, causing the wheels on the end truck to leave the track.
By contract, when a coach is traversing a dip in the track or when starting to ascend a climb, the wheels of the centre truck can leave the rails as the truck is suspended between the two outer trucks.Compensation
Another issue which needed to be addressed was to allow the wheels on the outer trucks to rock from side to side to cope with sections of track where one rail might be lower the the other. Normally, this isn't a major difficulty, provided the wheelbase of the vehicle is short. However, the Southwold coach is, in effect, a very long four-wheeled wagon which just happens to have an extra pair of wheels in the middle. Without compensation (ie suspension), there is no way the coach would remain on the track - the slightest discrepancy and one wheel would lift clear of the track.
Fortunately, I had already solved a similar problem with my Ford style railbus.
This too had a long wheelbase - though not as long as the SR coach. However, the principle could still be applied - keep one axle rigid and allow the other to rock from side to side (see How I added suspension to my Ford railmotor).
To achieve this on the SR coach, one of the pivot mounts for the end trucks was a simple ring bearing on the flat surface of the truck .......
....whilst the other truck had a longitudinal half-round bead along its length - thus allowing it to rock from side to side on the flat pivot mount.
Summary
Although the above may seem self-evident, they are the result of several months of designing, printing, prototyping, experimentation, re-design and re-testing to hone the way the coach performed. Even so, I discovered a couple of places on my railway where there was a hump and a dip which were too severe for the coach and so had to iron these out. I am pleased to say that I now have a rake of three Southwold Cleminson coaches and they perform well with no more derailments than any of my other stock.
Construction
Once I had finalised the design, construction was relatively straightforward, though the overall length of the coach means it has to be split in two (or three) to fit on the print bed (even though mine is 300 x 300mm).
As with most builds, I started with the underframe or floor - in this case the frame is separate from the floor. The two halves of the frame are identical .......
... and were glued together at the centre - with lugs and slots to ensure they matched up.
Once the glue had set (I use Tool Station thick / High Viscosity superglue) ......
... it was flipped over and the three floor sections were glued in place. The reason the floor was made in three sections rather than two was to provide some additional reinforcement for the joint between the two halves of the frame. The floor sections sit on a rebate on the upper edge of the frame. The two holes are to gain access to the bolts used as pivots for the end trucks. They will later be blocked off with removable plugs.
The sides of the coach were then glued into place. These are split into two halves. The two halves are slightly different - one has an opening toplight (see below) .......
..... while the other half doesn't. There is only one opening toplight on each side. The side walls fit into another rebate on the top edge of the frame to provide a slight overlap at the base of the side wall.
Once both sides had been glued into place, the ends were then glued in between them. It was fairly obvious where they needed to go - as you can see the ends are notched at the top to allow the curve of the roof to meet the upper outside edges of the side.
The support ring for one of the end trucks was glued into place next. A short piece of rod was put into the holes in the frame and the ring to ensure they aligned while the glue was setting.
The centre truck was assembled next. The W-irons/axle boxes are slightly different to those for the end trucks and are labelled 'MID' on the inside edge.
They were glued to the centre truck frame - trapping the wheelsets between them. I use Bachmann 24.5mm diameter metal wheelsets. I find they are fairly reliable and also provide a bit of additional weight to help keep the wheels on the track.
Before the end trucks were assembled, a 20mm long M3 bolt needed to be positioned in the pivot hole (it's almost impossible to insert it once the wheelsets are in place) .....
..... the W-irons were then glued on trapping the wheelsets between them. One truck was mounted on the bearing ring - the bolt being passed through and a couple of nuts threaded on to to act as a lock-nut.
Before the other truck was attached, two lengths of half-round bead were glued along the centre line, to provide rudimentary suspension/compensation.
The second truck was then bolted on to its mount. However, the nuts were not over-tightened to allow the truck to rock freely from side to side.
With the two end-trucks in place, attention was turned to the centre truck.
The centre truck was then put in place ........
..... before the other two brackets were glued.
An LGB self-tapping screw was passed through one of the holes in the linkage, and screwed into one of the arms from the centre truck.
A long pivot pin was then passed through the other hole and glued into the hole on the arm from one of the end trucks.
This process was repeated for the other arm on the centre truck.
The roof was made from four sections - two outers and two inners. The outers have a curved batten along the outer edge.
These were glued together and smoothed off with a file.
The steps were now glued to the ends of the frame beneath the balconies. I believe the SR coaches had steps only on one side as all their platforms faced the same way. On the PLR, with island platforms, I need steps on both sides.
Before the benches were added to the interior, the coach paid a visit to the paintshop. The trucks were removed to be painted separately. The wheels were masked with tape and the body and trucks given a couple of coats of Halfords grey primer from an aerosol rattle can.
The interior was masked and the exterior given a couple of coats of Halfords Vauxhall Burgundy Red from a rattle can. The railway's crests were printed on to self adhesive vinyl sheet, cut out and attached to the middle of each side.
The trucks and ironwork were painted black and the floors of the balconies and steps painted brown.
The interior was then hand-painted with brown acrylics,
The maker's plates were then painted and added to the sides of the frames - they also help to mask the joint between the two halves of the frame.
Glazing was then added to the sides and ends using 1mm clear acrylic sheet. I fixed this in place with clear Bostik adhesive - superglue has a nasty habit of making clear plastics go hazy.
The bench seats were assembled, ......
..... painted brown and glued in place inside the coach
Passengers were then added.
The assemblies were stained black and glued to the ends of the balconies and blackened brass chain glued between them.
Grab rails were made from 38mm lengths of 1.5mm diameter brass rod. 5mm at each end were folded through 90 degrees and then the handrails were slotted into 1.5mm diameter holes drilled beside the balconies.
The trucks were refitted and my own versions of hook and look couplings added - with integral Binnie medium Carmarthen buffers which can swivel with the couplings.
You can see all three coaches running in this video charting progress on the railway in 2022 (3m45s into the video).
Astounding Rik.
ReplyDeleteThanks for sharing this.
Cheers
Steve